Forensic schedule analysis.

Turn programme records into a transparent explanation of delay, critical-path movement, and time impact.

Forensic schedule analysis is the retrospective examination of programme records, including baselines, updates, logic, calendars and contemporaneous progress evidence, to explain how delay occurred, how the critical path moved and what time impact the records support. The method depends on the contract, forum and quality of data actually available.

The problem

Delay is rarely disputed in the abstract. What is disputed is why it happened, whose event caused it, and how much time it affected. Those questions are answered by the programme record, or they are not answered at all.

HKA's CRUX Insight research, drawn from more than 2,200 projects in 114 countries, found extensions of time sought by contractors averaged 65.8% of planned schedules and sums in dispute averaged 33.4% of contract budgets. Against that exposure, analysis quality is not a technicality. A model built on missing logic, retrospective constraints or unexplained duration changes inherits those defects.

Scope

Schedule health and baseline validation

Test the source programmes for logic, calendars, constraints, completeness and contract compliance before relying on them.

As-built reconstruction and update validation

Build a fact chronology and test progress evidence against the programme updates.

Critical-path and delay analysis

Explain critical-path movement, delay events, concurrency and pacing using records that can be reviewed.

Time-impact, windows and retrospective analysis

Select an appropriate method for the question and the available data rather than applying one technique by habit.

Demonstrative evidence and independent review

Prepare clear programme narratives, exhibits and reviews of an opposing analysis.

Capability transfer

Explain the method, assumptions and findings so the client team can use the work responsibly.

Method

  1. 01

    Validate the source data

    AACE International Recommended Practice 29R-03 treats source validation as foundational.

  2. 02

    Set the forensic question

    Define the event, period, contractual test and forum before selecting a method.

  3. 03

    Choose the method transparently

    Consider observational and modelled approaches, prospective or retrospective, and state their limitations.

  4. 04

    Analyse criticality and causation

    Trace events through the contemporaneous programme and records.

  5. 05

    Test sensitivity

    Document assumptions, alternatives and material data weaknesses.

  6. 06

    Report reviewably

    Use a chronology, explanation and exhibits that allow another analyst to reproduce the reasoning.

What you get

Schedule health and baseline validation report

Defect register against source programmes with materiality assessment.

As-built chronology

Fact chronology with source references.

Method selection memorandum

Method chosen, justification and alternatives considered.

Delay analysis report

Findings, windows, critical-path movement and time impact.

Demonstrative exhibits

Programme extracts, windows charts and comparisons.

Independent review report

Testing of another party’s schedule analysis.

What we need

Engagement

Engagement length and composition depend on the question, the available records and the required decision date. An initial discussion establishes scope; no published prices or generic duration promises are used.

Engagement shapeSuitable whereTypical duration
Schedule health checkEarly triage: whether the programme record is analysable.Confirmed after scope and record review
Single event or window analysisA discrete, bounded delay question.Confirmed after scope and record review
Full retrospective analysisMulti-event, whole-of-project delay position.Confirmed after scope and record review
Independent review or rebuttalTesting an opposing party’s analysis.Confirmed after scope and record review
Technical support alongside counselProgramme-side input to a live dispute.Confirmed after scope and record review

Scope limits

Frequently asked questions

It is the investigation of delay using CPM or other recognised schedule calculation methods and contemporaneous project evidence. Its purpose is to explain the significance of events in the programme network, including causation and criticality.

Initial discussion

Discuss a forensic schedule analysis challenge.

Share the project context, the decision required and the records available. The first conversation is used to establish whether the work is a fit.